    I've been logging my hours from the beginning. They include time on the couch reading the manual, watching videos and studying photos.
    Obviously the effort depends on your experience, options you selected, and any help you can get.

    Ultima estimates 350 hrs (400 hrs - 50 hrs for pre-fit)
    StepHours% CompleteComments
    Aluminum Panels307%I ordered Laser Cut Panels - I'm told it saves roughly 10 hrs.
    Pedals79%
    Ancillaries3417%
    Heater/AC1020%
    Hand Brake220%
    Gear Shift521%
    Steering623%
    Suspension925%
    Brakes627%
    Wheels127%
    Initial Suspension Setup328%
    Body Pre-Fit - Part 1028%I ordered Pre-Fit - I'm told it saves 60 hrs.
    Body Pre-Fit - Part 2028%
    Body Pre-Fit - Part 3028%
    After Pre-Fit 13536%I spent a lot of time thinking of layout options, specifically which buttons to install and where, where to install AIM and whether or not to install a stereo.
    After Pre-Fit 22843%Sidepod Ducts take a lot of time and patience. I spent 3-4 hrs per side.
    Body Final Fit - Part 14253%
    Body Final Fit - Part 21156%
    Dashboard Trims758%Should be 2, but I had to redo it.
    Carpets459%I also carpeted the walls.
    Seatbelts259%
    Seats260%
    Grills460%
    Glazing1063%Takes a lot longer than you'd think
    Sun Strip263%(estimate - not done yet)
    Wiper364%
    Mirrors164%
    Badges064%
    Gel Coat Repair465%
    Helicopter Vents065%I did not install these
    Carbon Fiber Aero Aids3073%
    Lights273%
    Front Canopy173%
    Rear Canopy274%
    Front Section375%
    Cockpit3583%Almost no documentation on AIM wiring. Required a ton of time researching.
    LT4 Charge Cooler685%
    LT4 Engine Cooling686%
    Dry Sump Reservoir487%
    Fuel System588%
    Air Conditioning389%
    Throttle Body189%
    Oil Cooling089%Literally took 5 minutes
    Engine Preparation590%
    Engine Mounts291%Should take 15 min, but I bought aftermarket and had some modifications.
    Cold Air Intake492%
    Accessory Drive292%
    Adapter Plate193%
    Clutch293%
    Gearbox Installation594%Includes sanding and painting
    Gearshift295%
    Drive Shafts396%
    Exhaust System497%Mine did not fit properly and they had to send shorter cats.
    Powertrain Control498%
    Add Fluids & Start Up!298%
    Debug/Fix Electrical Issues8100%1 missing loom wire. 2 bad loom wires.
    Total410